MoDOT to close lanes on I-70 and I-64 for surveying work as part of Improve I-70 project #2
ST. CHARLES COUNTY – The Missouri Department of Transportation will close lanes on Interstate 64 and Interstate 70 for survey work connected to the Improve I-70 Project #2. All work is weather permitting.
The following lane closures will impact locations on I-70 in St. Charles and Warren Counties and I-64 in St. Charles County nightly Sundays through Thursdays.
Starting the week of December 8 in Warren County:
- One eastbound and westbound I-70 lane between Route MM and Route 47 in Warrenton nightly from 7 p.m. to 7 a.m.
- One eastbound and westbound I-70 lane between Route 47 and Wright City nightly from 8 p.m. to 7 a.m.
- One eastbound and westbound I-70 lane between Wright City at Foristell nightly from 8 p.m. to 6 a.m.
On I-64 in St. Charles County, the following lane closures will occur the week of December 8:
- One eastbound I-64 lane between I-70 and Route K nightly from 8 p.m. to 5:30 a.m.
- One westbound I-64 lane between Route K and I-70 nightly from 8:30 p.m. to 6 a.m.
Starting the week of December 15, the following lane closures will occur on I-70 in St. Charles County:
- One eastbound and westbound I-70 lane between Foristell and Wentzville Parkway nightly from 8 p.m. to 6 a.m.
- One eastbound and westbound I-70 lane between Wentzville Parkway and Route A nightly from 9 p.m. to 5:30 a.m.
The Improve I-70 Project #2 covering the eastern portion of I-70 between Warrenton and Wentzville was awarded in November 2024. Construction is tentatively set to take place 2025-2028.
Missouri’s FY2024 budget from the General Assembly signed into law by Governor Parson provides $2.8 billion in General Revenue for the costs to build a third lane of I-70 across the state. The program will plan, design, construct, reconstruct, rehabilitate, and add a third lane in each direction on nearly 200 miles of I-70, from Blue Springs to Wentzville.
For more information on the Improve I-70 Program, visit www.modot.org/improvei70.